Is it possible to connect gas to an unregistered house: features of the connection and design of “unfinished”
The question of whether it is possible to connect gas to an unregistered house is of interest to many. Agree that gasification is not only a guarantee of comfort, but also a need for current realities. Since it is not very convenient to use gas cylinders, it is advisable to be patient, collect a package of documents and bring gas into the house.
It should also be noted that in case of sale of a house, the connected gas will increase the value of the property. We will tell you what documents are required to conduct gas to an unformed home, all stages of the procedure, and also help to make the process as simple and quick as possible.
The content of the article:
Conclusion of a gas supply agreement
Gas equipment is notable for its simplicity, safety and environmental friendliness; blue fuel attracts with environmental priorities, low price, and ease of use.
According to the Federal Law "On Gas Supply in the Russian Federation" No. 69-ФЗ dated 03/31/1999, the following are involved in gas supply:
- gas distribution organizations involved in the transportation of raw materials to consumers;
- a gas transportation organization engaged in pumping gas through gas pipelines (leased or own);
- gas transmission system - is an intermediary between the producer and consumer of raw materials;
- gas supply organization - concludes an agreement with the consumer for the supply of gas.
In order to conclude an agreement, an individual draws up an application (offer), where he announces his intention to join the gas pipeline.
The first step towards gasification is the submission of an application (offer).
Making gasification at home
To get permission to laying a gas pipeline to a private house you need to collect an impressive package of documents and go through four stages:
- receipt of technical specifications;
- project development;
- installation of gas pipeline equipment;
- connection.
Required documents:
- an application for gasification from the owner of the property;
- passport of a citizen of the Russian Federation;
- document of ownership, where gasification is planned;
- if the pipeline will be laid through neighboring sections, the written consent of their owners for such a procedure is necessary.
Often owners start the gasification process when the house is still under construction. Naturally, they are interested in whether it is possible to carry gas into an unfinished and yet unformed house?
In this case, in addition to the documents listed above, it is necessary to provide additional papers:
- ownership of the land where construction is carried out;
- a copy of the registration certificate for the building under construction, instituted by a notary public;
- application for technical specifications (technical specifications);
- written confirmation of the territorial state authority on the legality of construction work.
The connection of an unregistered house is carried out as gasification of an auxiliary building, and not a residential one.
Obtaining technical conditions
TU are necessary in order to design an outdoor gas pipeline and an intra-house gas supply system. To obtain the technical specifications, you should contact the gas service to determine if there are enough power to connect.
Required Papers:
- land ownership;
- floor plan of the house or permission to build it (must be certified in the district "Architecture");
- site plan on a scale of 1: 5,000;
- a statement signed by the head of the Gas Trust.
The minimum preparation time for technical specifications is 2 weeks. The term may be extended up to one month. In practice, coordination takes much longer.
The validity of the technical specifications is up to two years. After this time, the gas pipeline should be built.
Gas supply project development
After the owner receives the technical specifications for the supply of gas, a project is being developed.
The following package of documents must be provided to the design organization:
- TU;
- geodetic survey of a personal plot with all communications and buildings with reference to the terrain;
- all documents for the construction;
- for the gasification of a non-residential house (unfinished), a statement of technical characteristics is required (the building must be ready at least 70%).
After that, you should call the wizard, who will carry out all the necessary measurements and draw up documentation. The project is reviewed within 15 business days. The next step is to pay for the project. The cost of the service depends on the distance of the facility to the gas pipeline.
The project takes into account all gas appliances that are planned to be installed in the house (floor boiler or wall-mounted instantaneous water heater, gas stove, fireplace, etc.). This is done in order to calculate the required amount of raw materials.
The consumed gas volume is indicated in the equipment certificate. In addition to this, it is also necessary to provide a plan for the arrangement of devices in the house.
The field of how paperwork is passed, installation and construction work begins.
Registration of power of attorney for gas connection
Gasification is a difficult and lengthy process. Not all owners have enough free time to personally deal with this issue.
In this case, a power of attorney is issued for a private person who represents the interests of the owner of the house. This document must be certified by a notary and attached to other papers.
Gasification of a private house: new rules
On June 6, 2019, the "Rules for the Design of Gas Consumption Systems" (SP 402.1325800.2018) came into force, according to which, permission to gasification of private houses will be issued only after all requirements are met:
- Gas boilers are allowed to be placed in the basement or on the basement. In one room, the installation of no more than two gas boilers or water heaters is allowed.
- In special rooms it is allowed to install only double-glazed windows, which can be easily knocked out if necessary.
- In the living room must be present devices that monitor the temperature and pressure in the gas system, as well as meters that take into account gas consumption.
- All gas equipment must be certified and have all the necessary documents.
- The connecting hoses must be no longer than 1.5 meters and sealed.
- When installing a gas stove, the distance to the opposite wall should be at least a meter.
- The gas stove must comply with GOST 33998, have a gas control system, as well as a dielectric coupling between the valve and the hose to protect against stray current.
The height of the ceilings in the kitchen should be at least 2.2 meters.
To ventilate the room requires a window, hood and clearance under the door.
Choosing a contractor for gas
When the question of how to transfer natural gas to an unfinished house is resolved, and the project is ready, the owner must choose an organization that will deal with the gasification of the building. It must have a license and be registered in the GORGAZ registry.
Those who do not want to cooperate with GorGaz, its employees issue technical specifications for the development of the project. This document should be contacted by the selected organization.
Some companies are engaged in installation and design work. A comprehensive order of services will save up to 25%. To prevent misunderstandings, it is recommended to conclude a contract with the installation organization.
At the design stage, you need to be as careful as possible. It is necessary to take into account not only technical, but also aesthetic parameters, since reconnecting and transferring gas equipment requires coordination with the gas service and financial costs.
After the gas pipeline and related equipment are installed, the new gasification facility should be adopted by a special commission consisting of GORGAS employees. The commission checks the object only if it is completely ready to connect. Consideration of the issue takes at least two weeks.
The maximum term is one month. If no violations are found, together with a positive response, the owner receives a receipt for payment of the technical supervision decision.
It is strictly forbidden to independently engage in laying a gas pipeline, as well as installing gas distribution indoors, and it is strictly forbidden to connect gas equipment. All unauthorized actions are subject to a fine.
The cost of gasification of an unfinished house
The cost of installation work for all organizations is different. The price is also affected by regionality.
The connection cost includes:
- gasification project fee;
- earthwork (if necessary);
- tie-in into a street gas pipeline;
- gas pipes (internal and external);
- installation and connection of the counter.
If the throughput of the gas pipeline is exhausted, then connection is not possible.
All gas appliances must remain in place. They can only be moved after agreement with the gas workers. GORGAZ employees have the right to go home and check their existing plan with the actual location of the equipment and, in case of non-compliance, levy thousands of fines.
Conclusions and useful video on the topic
Important points when conducting a gas pipeline to a house:
All about gasification of a private house:
Gasification process from A to Z:
You can carry gas into an unfinished house. The procedure is almost identical to the gasification of a residential building. There are only minor differences in the list of documents. If you don’t have time to run around, instruct intermediaries. To do this, it is enough to issue a power of attorney.
Did you carry gas to an unregistered or unfinished house, step on a rake and brilliantly cope with difficulties? Do you have experience with the gas service or do you know which organizations are best to stay away from? Or maybe you have some valuable tips that will help you avoid mistakes? Share your experience in the comments and ask questions to experts.